- Pre-haul road maintenance on the Moser Roads will occur this summer
- Skyline yarding will occur in Moser area into July
- Small diameter tree thinning and piling in Moser Creek and Leverich Gulch
- All ground-based tractor logging units are complete
- More than 400 acres of small diameter thinning is currently occurring, and will be implemented throughout the summer. This work is completed by hand-crews, leaving small piles throughout the under story. The piles will then be treated with prescribed fire during the winter months.
- Log decks from last winter and from the skyline logging will be hauled out this summer
- Additional tree marking and contract preparation for future helicopter treatments will be occurring this summer